Reporting Point Backflush in REM

Former Member
0 Kudos

Dear all,

Consider the following scenario for RP backflushing in REM:

Total quantity produced on the line : 2 pc

There is one intermediate reporting point and one final reporting point.

REM profile <b>0004:Report. points with activities</b> is being used.

Now, at the intermediate RP i confirmed 1 pc.

At the final RP the system allows me to confirm 2 pc with a warning.

How do i prevent this? I want the system to only allow as much quantity to be confirmed as has been confirmed at the previous RP.

Kindly advice.

Regards,

Sumeet

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184655
Active Contributor
0 Kudos

Dear Sumeet Vaidya,

Please give a try with this user exit <b>XMRM0001</b>.We used for a different

purpose during backflushing.

I'm not sure whether this user Exit works for this reason.

Please check with your ABAP consultant for more details.

Please check & confirm

Regards

Mangal

Former Member
0 Kudos

Hi summet,

your are correct, system allowing to backflush qty grater than previous reporting point with warning message.

i doknow if there is any user exit to prevent this.

However u can use MF26 , to view reporting point information.

This will show backflushed quantities at each reporting point

Regards

Pradeep