on 10-15-2017 11:07 PM
Hi Team,
I need your suggestions.
New plant is created , V1 stock material are 2140 , when I tried to run MRP in MD06 , I am getting ” No elements exist for the selection” is coming, list of materials are not coming. I have verified MD21 ,Planning file entries , 61 Materials are available.
Can you tell me why it is not coming in MD06
I tried in MD05 also , it is not coming,
need your support to resolve this issue ASAP
Regards
Hi Mahesh,
Your explanation is good, Thanks for your quick response.
As you said, I have run the MRP in MD01 , It is generated below message
Materials Planned : 61
Materials with new exceptions : 4
This 61 materials same I have seen in planning profile ,and I verified the report in MD05/6 , still I can't see the list of materials in the report.
can you suggest me quickly.
Waiting for your response
Regards ,
Sudheer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI Sudheer,
MD05 and MD06 are reports which is used to see results after taking MRP run , for running MRP we have to use
1. MD01- plant level MRP (all the materials under plant will planned)
2. MD02 - Single item multilevel ( used for one material MRP all the sub assemblies of the material also planned)
3.MD03 - single item single level( used for one material planning wtihout considering its sub assemblies).
first run the MRP as for the requirement then use the t codes you can see the data.
Regards,
Mahesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mahesh,
Thanks for your response. Problem solved.
One clarification required on MRP process, I have processed MD01 on the plant level, as per MD01 purchase requisition created , where can I check only PR's which is created by MD01. We have MD05/MD06 , but I can see all materials. Do we have any alternative to check. if yes , pls let me know.
Regards,
Sudheer
check your material master record (particular material you run) in MM02 second (MRP1-4 TABs)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
check all your new plant settings in OPPQ first
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.