Hi,

for PO release M_EINK_FRG is the object.

but along with this we need to give M_BEST_BSA & M_BEST_WRK, the activity is 02(change).

my concern is, if we give him the same objects authorization, he will be in a position to change the PO also, along with releasing the PO.

do we have any control for the same?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hii,

I think Releasing authority have the authority to change the PO.

Regards,

Former Member
0 Kudos

yes u r right ,

but we dont want lower level releaser to change it.