while executing MF60, i am facing the issue that in case if any common material is already staged for some other requirement (Process order),the system does not show any requirement for the same as it considers the stock of the common material in that particular storage location Unless the consumption of that common material,the system does not show any requirement to stage.

I can understand this is SAP Standard behavior but can any one help me how i can stage material for a different process order unless the previous Process Order was not clear ?