CAN RECEIVING PLANT CREATE STOCK TRANSPORT ORDER FOR THREE SUPPLYING PLANT BY MRP

Oct 13, 2017 at 02:34 PM

36

avatar image
Former Member
  1. Earlier We have one Main supplying plant in that three storage location & each reeving plant create STO to main supplying plant.
  2. Now business changed the design the One Main supplying plant in that three storage location , the three storage location changed to Plant means it becomes 4 Supplying Plants.
  3. The challenge is One Receiving Plant say (100 Qty ) it should check the stock of the 4 supplying plant say each plant has 25 qty. and create STO get the material from the 4 supplying plant.
  4. We are working in ECC and We have MRP planning with ROP setup and Lot size EX. all plants within Same Co code.
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Oct 13, 2017 at 05:05 PM
0

Hello

This is not possible in the standard system and this question has been already asked (and answered) several times in SCN.

Basically, MRP will not check the stock in the supplying plant before the creation of a stock transfer. You can implement your own logic in BAdI MD_MODIFY_SOURCE to select the source of supply during the MRP run.

Regards,

Caetano