CAN RECEIVING PLANT CREATE STOCK TRANSPORT ORDER FOR THREE SUPPLYING PLANT BY MRP

  1. Earlier We have one Main supplying plant in that three storage location & each reeving plant create STO to main supplying plant.
  2. Now business changed the design the One Main supplying plant in that three storage location , the three storage location changed to Plant means it becomes 4 Supplying Plants.
  3. The challenge is One Receiving Plant say (100 Qty ) it should check the stock of the 4 supplying plant say each plant has 25 qty. and create STO get the material from the 4 supplying plant.
  4. We are working in ECC and We have MRP planning with ROP setup and Lot size EX. all plants within Same Co code.
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Oct 13, 2017 at 05:05 PM

    Hello

    This is not possible in the standard system and this question has been already asked (and answered) several times in SCN.

    Basically, MRP will not check the stock in the supplying plant before the creation of a stock transfer. You can implement your own logic in BAdI MD_MODIFY_SOURCE to select the source of supply during the MRP run.

    Regards,

    Caetano