Hi,

In CK11N costing run, in the dates tab, how can we keep the 'cost to' date to be defaulted to 12.31.9999 every time we do the cost estimate, right now the date is 12.31.2007.

Thank you,

Nivi

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Do the necessary config in

Controlling>Product Cost Controlling>Product Cost Planning>Material Cost Estimate with Quantity Structure>Costing Variant: Components-->Define Date Control

Good Luck

Hari

Answers (1)

Answers (1)

Former Member
0 Kudos

use T.code OKK6 and do the necessary changes.