on 12-05-2007 12:31 AM
Hi,
In CK11N costing run, in the dates tab, how can we keep the 'cost to' date to be defaulted to 12.31.9999 every time we do the cost estimate, right now the date is 12.31.2007.
Thank you,
Nivi
Hi
Do the necessary config in
Controlling>Product Cost Controlling>Product Cost Planning>Material Cost Estimate with Quantity Structure>Costing Variant: Components-->Define Date Control
Good Luck
Hari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
use T.code OKK6 and do the necessary changes.