Hi,

In CK11N costing run, in the dates tab, how can we keep the 'cost to' date to be defaulted to 12.31.9999 every time we do the cost estimate, right now the date is 12.31.2007.

Thank you,

Nivi

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 10:48 AM

    Hi

    Do the necessary config in

    Controlling>Product Cost Controlling>Product Cost Planning>Material Cost Estimate with Quantity Structure>Costing Variant: Components-->Define Date Control

    Good Luck

    Hari

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 11:45 AM

    use T.code OKK6 and do the necessary changes.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.