How does the Production Schedule Profile

Hello

Some of the important functionalities of production schedule profile(PSP) in work sheduling view are

1.Scheduling with the order release

2. Auto Goods Reciept

3.Capacity Profile

4.Determines order type when planned order is converted in production order

Now, I am maintaining all of the functionalities without using PSP

say when we convert planned order to production order in MD04, it takes to CO40

where we schedule, do capacity check and release the production order <b>without maintaining Production schedule Profile</b>

Assigning of the order type can be done in CO01 ( not sure in C040)

How does <b>Production Schedule Profile influence in planning</b> <b>& Production activities</b>

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 12:53 AM

    Hi Eshwar,

    I did not understand, waht you are implying to. Production scheduling profile helps you to release orders automatically when you convert planned orders to production orders. Automatic good receipt is performed and some confirmation activities automatically. In process industry it creates control receipe and batch automatically. PSP performs these steps automatically, instead you doing them step by step.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Thank for your reply

      In MD04, when we convert planned order to production orders - we reach to CO40 where we realease the production order manually ( Green flag)

      Instead of realeasing the production order manually we can use the <b>production schedule profile to realease the production order automatically</b> (so there is no need to click on green flag manually in CO40 for releasing the production orders) , where after systems does capacity leveling and post automatic goods reciepts

  • author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 09:51 AM

    Hi

    Assign this production scheduling profile to the production scheduler and. I think we have to assign the production scheduler to the the plant please check it up. Then only this work

    Regards

    J.S

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.