While changing PR, I want that release strategy should not be triggered if quantity is reduced or line item deleted even if value limit is crossed.

But it should trigger according to value limit when the quantity is increased or line item added.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 04:01 PM

    Hi Balaji,

    When you change the qty obviously your value will also change.So release will work for the value only.What else you want?

    regards

    venkadesh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 04:02 PM

    Hi Balaji ,

    I think its not possible

    Eventhough you can try this way

    Try changing Changable indicator in release strategy to 4 (Please check)

    In spro>mm>pur>pr>rel str>rel indicator in changable column there are 5 to 6 options please check

    BR

    Diwakar

    reward if useful

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.