Hi all,
when I have changed a program at production side that is already being used in live systems, it asks me request to change the code, I create new one and want to carry this into live system;
however I cannot, it just says it has been released and now the lock of the object has gone(something like that), but I cannot see it at<b> stms</b> transaction side; what is the problem?
Thanks.
Try unlocking the request from transaction SE03 -> Unlock Objects (Expert Tool)
Hi!
Mostly the transport routes are defined this way: developer system -> quality control system -> production system.
If you modify a program in the productive system (which might NOT happen in most common), it will ask you for a new transport request, but because this system is the last in the line, it will go nowhere. Modifications will be live immediately after the activation.
Regards
Tamá
Hi
if the transport request is released from your side for the privious vertion then again if you want to change the changes then you need to create a new request for that program
because i think you already released the transport request 1st time don't save under that transport request
save under new transport request