Delivery is being created before material availability date in the sales oredr, can any one tell me how it is possible?
For ex: order was created on 11/12/2007 and requested delivery date was 11/29/2007, due to which system proposed MOD on 11/28/2007.Transit time is 1 day and customer will receive material on 11/29/2007.
But,system allowes me to create delivery on 11/15/2007,I wonder how it is possible.
Thanks
Hi Ravinder
Check the document flow.
1) Note that the delivery document flow date<b> is not the MAD date</b> .
2) In SAP , you can create delivery document today <b>even if MAD date is in future</b> .The document creation date logged onto the document flow would be today's date.
3)To execute the delivery document you need to enter the <b>selection date >= MAD date</b>. <b>The planned pick date would always be the MAD date</b>.
4) PGI date would be the date on which PGI document is created.
5) Billing date would be the date on which Billing document is created.