Std. Cost estimation

Hi all,

How do we maintain standard cost estimation for the material master?

Its very urgent

i will assign the points

venu

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 06:36 AM

    Hi

    Using T-code CK11N and save it

    then using CK24 you mark up and release the std cost estimate.

    Best Regards

    Ashish Jain

    Message was edited by:

    Ashish Bohara

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Venu,

      System will pick price from different location:

      Example:- Raw material price form Material master Accounting data,

      Overheads calculation from Costing sheet

      Activity price from KP06(where we maintian plan activity price)

      Hope this will help you

      Best Regards

      Ashish Jain

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.