on 10-12-2017 7:34 AM
Hi,
Using a ABAP acquisition program the asset value date was entered as 31.00.2017 by mistake and now we are not able to reverse the document also. When we tried to reverse in AB08, it says invalid date. Is possible to change this wrong date at table level, how can document reversal enabled?
Regards,
Sathesh
We were still not able to reverse. But as a work around we transferred the asset to a new asset with the correct AVD.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sathesh,
Can you share screen shorts here.
From you want to change the asset value date?
Thanks and Regards,
Udaykumar P.P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sathesh,
As far the situation concerned, it is something strange, I am wondering how the system allowed to post such entry.
In your quality testing system, using the programme, please try to make same entry and see whether SAP allows such entry again.
If incase programme allows such entry to make, then try making the reverse using the same programme.
Thanks for your time.
Thanks and Regards,
Udaykumar P.P.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.