prod alt plant

hi experts,

actually there is a requirement of material A for plant X. but material A is produced in plant Y. so i nhave given production at alternate plant special proc 80 and E,

when i run mrp i am not getting planned orders for material A and its child items. please revert back with your suggestions thanks.

sanjeev

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on Dec 04, 2007 at 05:21 AM

    Hi sanjeev deshpande,

    You just check the customization setting in "OPPQ'' T.code for your "A" plant parameter for Special procurements Key 80 there is you minted your plant "Y"

    and again take the MRP your problem resolved.

    Hope this will help you and reward for every suitable answered.

    Regards,

    Rajesh Tayade

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 04, 2007 at 05:49 AM

    Sanjeev,

    You need to maintain the special procurement plant as "Y" in the defination of Special Procurement key "80" in Plant "X". This you can do with transaction OMD9.

    Regards,

    Prasobh

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 06:33 AM

    Hi,

    In your case planning plant is X and Production plant is Y.

    1.Do settings for special procurement key (80), as our experts suggested. Also ensure following settings Special Procurement = “P”, Plant =’Y”

    2.Assign the SPK to material (A) in Planning Plant (X).

    3.Create Material (A)and BOM in production plant (Y)

    4.If you run the MRP at planning plant, planned order will be created for Material (A) based on demand and stock.

    5.Dependent requirements will be created in for components in production plant. Now u can start production at production plant if there is no enough stock.

    6.Convert the planned order for planning plant to production order, GR will increase the stock at planning plant.

    plz come back if ur problem is not solved

    regards

    pradeep

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 08:53 AM

    hi sanjeev,

    as our members said you need to do settings. so that you will get planned order for A in plant X. then you need to run MRP in the Y also to get dependent requirements of components which comes under BOM of A material.

    hope you may get solved

    RObert

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.