The issue that I am having is that we have created a PO with a freight condition. Instead of the price for the condition being for one 1 ton it was for 1 pound. There was a goods receipt already done for this line item. I have tried to back out the receiver and then change the conditions. However it tells me that since we are on the Moving average price that the price for the material will be negative and will not allow me to back it out. Im not sure if when I did get it backed out that it would work. Please let me know how I can make the changes or let me know the process that I need to go through to get this fixed. Thank you very much for you help.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 03, 2007 at 03:48 PM

    You can correct the freight price during invoice verification.

    There is an OSS message regarding price will be negative error. You may want to have a look at it as well.

    Lakshman

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.