Dear,
While doing settlement for a Production order through Tcode-co88, the balance lying in that order is going to PRD account and i have configured that balance to be settled to COPA. But while doing the same i am not getting COPA document.
Pls suggest where i have done mistake..
Thanks in Advance..
Janardhan.
Hi
Check in your settlement profile, whether you have ticked the tab "variances to costing based PA"
regards
Ram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Janardhan,
Check the value fields. Value fields for updation in COPA are determined by PA transfer structure which is assigned to Order. (I assume it is a costing based COPA).
S Jayaram
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.