Hi experts

I created the process order and did the consumption and TECO for the order. Due to some reasons i revoked the TECO. Here i am facing the problem.

Initially some raw materials are not batch managed. Now in the mean time MM team has activated the batch management active for all raw materials.

When revoke the TECO now, the system asking the batch number for raw materials, the batch number column is not editable now. I am not able to do the revoke of TECO.

How to rectify it?

Thanks in advance

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Dec 03, 2007 at 11:32 AM

    you can deactivate the concern material from batch management

    or else post some stock with batch number for that material and give the number

    give me the reply how it works

    sasikanth

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 04, 2007 at 12:12 PM

    Do reverse posting for all ROH (262) then again re issue the ROH with newly craeted Batch.TECO only not allow user to change the Production Order.We can able to post the material even after TECO.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.