Skip to Content

refactor of calculation view which is referenced by a scripted calculation view

Hi there,

I am trying to refactor a calculation view which is referenced by a script based calculation view

Basically I am trying to move the first view into an other package. However I am getting an error message saying that the view is being used by a script based calculation view.

Any idea how to get around this?

Regards, Thomas

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Oct 16, 2017 at 03:13 PM

    Yes, this is really a problem.

    As a workaround you can do like this:

    1. Copy your Calculation View to the new package with the same name

    2. Edit your scripted view -> change package-name of calculation view from old/new

    3. Delete the old view

    Best Regards

    Add comment