Hi,

we want to execute the dep. monthly in background.Can we execute the all months at a time in background? Please give your valuable advice as early as possible.

Thanks in Advance

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Dec 03, 2007 at 10:01 AM

    hi Nagi,

    you can run as 'Unplanned posting run' then it will be run for all months. For example, last run you had in January and you run now for December, and if you tick (like above), than it will calculate and post between February and December.

    hope this helps

    ec

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 02:41 PM

    Hi,

    You can do it in the following way.

    1) Create a different variant for each month

    2) Schedule a background job for these variants sequentially ( for ex. Jan, Feb.. Dec). Ensure that there is sufficient time gap between the start times of each variant

    3) Ensure that the posting periods are open for all months

    Remember that if one of the jobs fail the rest will fail too.

    Thanks

    Jagdish

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.