Hi experts,
I am new in SAP PP
currently when run the MRP, it will generate planned orders and PR's. it will calculated planned order sub compoents requirement qty also.
but i want to change settings for once convert planned order to production order once release after only need to create sub compoent PR's and planned order
pls explain what change need to do?
Regards,
Elango
Hi
This is not possible,because planning and production order releasing is two different activity.When ur release production order thats mean ur giving green signal for manufacturing or start manufacturing and when ur release the production order ur work center or capacity is get booked against that production order. So at the time of production order release if u want to plan the child item then u have to procure ur child item then u have start manufacturing so complete time ur capacity is showing as loaded then ur not able plan for other production order.