Hi All,

My requirement is as follows:

When I create PM orders for stock item, system generates a reservation number.

But the actual qty is sytem for such items are less than planned qty or NIL qty.

How to create PR's for such items automatically by system ?

Is MRP run required to be activated for such items (i.e: maintenance of MRP views in material master) or any other way to do it for stock items (L) ?

If so, what all fields need to be filled in material master?

Is there a way for doing MRP run only for material type ERSA (spare parts) or only against reservation numbers created through maintenance orders or against MRP controller?

Kindly post your valuable feedback.

Thanks in advance and best regards.

Kannan J

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 05, 2007 at 10:31 AM

    Dear Shiv,

    In addition to the setting adviced by another expert you must give special procurement key in MRP view 2 of Material Master for example Subcontract-30.

    to enable material to be planned through MRP.

    I hope this will be useful to you & if so reward points,

    Vivek Maitra

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Dec 03, 2007 at 07:50 AM

    Hi,

    For automatic p.o creation, you can use reorder point.

    In material master mrp1 view, use mrp type VB, reorder level ex. 50 pc.

    Maintain lot size HB, maintain max stock level 100 pc.

    When the requirement comes it will consume from stock. If the stock goes below reorder ponit(50), it will create planning file entry.

    When you run mrp (MD01), it will automatically create p.o.

    But without running mrp, system can not create p.o

    With that you can maintain your stock.

    Hope it will help.

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.