please guide me for my scenario given below:

how work center is to be decided whether machine wise or tool wise.because one macine can be load by four different tool at a time.

Regards

Deepak Sharma

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Dec 03, 2007 at 06:44 AM

    Deepak,

    Workcenters are decided by Machine wise, Tools are defined as PRT(Production Resource Tools) in SAP.

    In the routing for the product we use the workcenter(machine) and also assign the relevant PRT to the operation.

    Regards,

    Prasobh

    Addtional inofrmation added

    Message was edited by:

    Prasobh Karunakaran

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      I would like to describe you with one example.

      Suppose there is one product named 'X'. This X product has 20 tools and we have 176 press machine. Now this 20 tools of product 'X' can be loaded at any work center among 176 simultaenously. Now how many routing should I make. I can not dedicate the press for these 20 tools.In one press I can load 4 tools simultaenously.

      I think you are now clear with my problem.

      Regards

      Deepak

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.