How to calculate delivery date of PR

Dear experts,

I want to calculate the delivery date of purchase requisition item in the program which is proposed in PR creation. Anyone can give me the function module or subroutine for this?

Many Thanks,

Tony.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 03, 2007 at 06:52 AM

    Hi,

    It includes "processing time for purchasing + planned delivery time + GR processing time".

    Processing time for purchasing in tcode OPPQ (process time for purchase)

    Planned delivery time in mrp 2 view (Time taken for deliver)

    Goods receipt processing time mrp 2 view.(Inspectoin and Storage)

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.