cancel
Showing results for 
Search instead for 
Did you mean: 

MRP - Schedule Line for Multilevel BOM

Former Member
0 Kudos

I have a BOM-- multilevel

When we are running MRP the system calculates the Schedule lines for the components , the thing is it takes the Maximum Lead time of 21 days which has been maintained in one of the components , the System takes this as the schedule line for the other item which is having the lead time of 6 days only .

please guide me why system is taking the max. lead time for all the items .

If i need the schedules according to the items how i can proceed

Regards

R.Rajaram

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

The system should have taken like this:

In one of the level of BOM, if one component has lead time 21 days, the other component has 6 days .This lowest lead component procurement should start last 6days of 21 days period..

It should be like this only.

Hope it is clear, else get back.

Regards

YMREDDY

Former Member
0 Kudos

> Hi

> The system should have taken like this:

> In one of the level of BOM, if one component has lead

> time 21 days, the other component has 6 days .This

> lowest lead component procurement should start last

> 6days of 21 days period..

> It should be like this only.

> Hope it is clear, else get back.

> Regards

> YMREDDY

Dear Reddy

The need is the lowlevel item, i need in the initial stage itself and the other one can be after 21 days, so what i need is the system should create schedule lines taking that 6 days in to consideration . can you suggest how we can achieve this.

Regards

R.Rajaram

Former Member
0 Kudos

Hi

You should maintain the master data properly.

workcenter : yopu should maintain capcity header :

fields:

active verison : should be maintained.

either standard avaiable capacity or interval of available capacity to maintained.

Relevent to finite scheduling should be checked.

Formaulas in capcity & schediuling to be maintained.

Controlkey should allow capacity & schedulung.

MRP settings:

under step: Define scheduling parameters for planned orders ( TCODE: OPU5).

should be maintained.

Finally MRP control parameters in the intial screen of MRP run select " lead time scheduling & cpacity planning for the field : scheduling,.

with the abopve settings you should be able to achieve your results.

Hope it is clear. else pl. update.

Regards

YMREDDY