Operation subcontracting

Hi,

Friends i have some confusion regarding operation subcontracting if anybody knows the flow & using successfully in project pls give me ur steps which clear me operation subcontracting.

Thanks

shiv

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 03, 2007 at 05:09 AM

    Hi shiv,

    suppose you are having 3 opreations like 10 ,20, 30. For 20 th your doing operation subcontracting.

    steps are as below,

    1.create info record (ME11) for vendor.

    2.In routing For 20 the opreation assign the control key allowed external process (PP02),assign Info record numer External tab of operation (Ca01)

    3.Create demand and Run MRP, convert planned order to prod order.

    4. confirm 10th operation.

    5. Now system create PR for 20 th operation. this u can see at operation overview of 20 th operation at CA02.

    6. Convert PR-> PO using ME58.

    7 send the material TO VENDOR through ME2O

    8. Receive the material Against PO through MIGO (mvt 101)

    9. confirm the 20 the operation.

    regards

    pradeep

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.