Hi Prabhu,
First create Purchasing orgainisation
Path:IMG...>Enterprise Structure....>Materials Management....>Maintain purchasing organization
Assign Plants to the purchasing organsation
Path:IMG...>Enterprise Structure....>Assignment..>Assign purchasing organization to plant
note : assign all plants irrespective to the company code (its is the central Pur org)
Assign purch. organization to reference purch. organization
this purchasing org , must be ur ref pur org
then for the vendor extend the pur cahsing view for this pur org
now create a contract
using this pur org with out mentioning any plant
and u can release release orders for this contract for all the plant u have assigned for this Pur org
Hope it wud have answered ur question
Reward if useful
Aasif
well while creating the contract do not mention the plant on the intial screen and once ur on next screen use edit---.>plant condition on menu bar if u want to make some plant specific settining