Hi,

in my work center if i assign a personel number can the capacity of the machinn be 0 when the person is on leave. can this happen

rgs

madan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Madan Mohan,

In such work center you would have created two capacity categories name-001 for machine & 002-for labour,Here in your case the machine capacity will still not be reduced,only the labour capacity will get reduced ,machine capacity will get reduced only when the machine is under break down & PM guys blocks the capacity for maintenance purpose

Hope my explanation in understandable for you

pls revert back if u have any doubts & reward points if useful

Regards,