Maintenance Order Confirmatin Parameters

Former Member
0 Kudos

Dear All,

Can anyone tell me the how man power calculation occurs with any example.... and do tell me meaning of major fields in Order confirmation screen...

Thanks

DM

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member187991
Active Contributor
0 Kudos

hi deepak

if you can pin point your requirments it is easy to explain other than general view, whether you want the manpower cost or manpower itself

regards

thyagarajan

Former Member
0 Kudos

Hi,

Following are fields that we used to fill during confirmation: plz tell the impact/ relevance of these fields.

Actual Work

Remaining Work

Work Starts on

Actual Duration

Work Ends on

Forecast End

Reason

Confirm. text

TOTAL CONFIRMATION DATA

Following are the fields that are based on some Calculation, can u plz highlight them ???

Cum.Actual Work

ActDuratn

Forecast work

PlannedDuration

i will be gr8ful

RGRDS

DM

former_member187991
Active Contributor
0 Kudos

hi deepak

These fields were updated to the Time management if youhave activated the same,it is just an information as part of PM where as if you enter in time management you can evaluate the performance of the person

regards

thyagarajan

Former Member
0 Kudos

Thanks but i think we have to enter the below fields during confirmation of order in IW41 ?????

Actual Work

Remaining Work

Work Starts on

Actual Duration

Work Ends on

Forecast End

Reason

Confirm. text

former_member187991
Active Contributor
0 Kudos

hi deepak

yes we have to enter these fields while doing confirmation becaus it has to update in PM component.

<b>Confirmation of Time Data</b>

You can confirm the following time data:

Who processed the operation/sub-operation

Example:

The operation was processed by an employee with personnel number D001760 at work center ME-01 in plant 0001.

How long the work took and the period in which it occurred

Example:

The operation required three hours work. The work was started at 9.00 on 1/12/1997 and finished at 12.00 on the same day.

What activity was performed

Example:

The activity type entered for the operation was "working time".

How much longer work must continue

Example:

The remaining work required for the operation totals five hours.

How much of the operation time was used (duration)

Example:

The operation has lasted five hours (until now).

However, the work duration totals only three hours.

This scenario could occur, for example, if the operation involves painting an object:

The painting work takes three hours. The paint then needs to dry for two hours. Only then can work on the object (or the next operation) be continued.

When is the operation expected to be completed

Example:

Since this operation can only be worked on for three hours each day, the estimated completion time (Forecast end) is at 12.00 on 1/25/1997.

Whether the work for this operation/sub-operation is completed

Example:

Once the painting planned in the operation is finished, the employee entering the last confirmation flags the operation as "finally confirmed".

Whether the reservations still outstanding should be cleared

Several pots of paint were reserved for the painting work. However, not of all them were used. The employee entering the completion confirmation indicates that the outstanding reservations should be invalidated.

A free text

regards

thyagarajan