Maintenance Order Confirmatin Parameters

Dear All,

Can anyone tell me the how man power calculation occurs with any example.... and do tell me meaning of major fields in Order confirmation screen...

Thanks

DM

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Dec 03, 2007 at 03:47 AM

    hi deepak

    if you can pin point your requirments it is easy to explain other than general view, whether you want the manpower cost or manpower itself

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

    • hi deepak

      yes we have to enter these fields while doing confirmation becaus it has to update in PM component.

      <b>Confirmation of Time Data</b>

      You can confirm the following time data:

      Who processed the operation/sub-operation

      Example:

      The operation was processed by an employee with personnel number D001760 at work center ME-01 in plant 0001.

      How long the work took and the period in which it occurred

      Example:

      The operation required three hours work. The work was started at 9.00 on 1/12/1997 and finished at 12.00 on the same day.

      What activity was performed

      Example:

      The activity type entered for the operation was "working time".

      How much longer work must continue

      Example:

      The remaining work required for the operation totals five hours.

      How much of the operation time was used (duration)

      Example:

      The operation has lasted five hours (until now).

      However, the work duration totals only three hours.

      This scenario could occur, for example, if the operation involves painting an object:

      The painting work takes three hours. The paint then needs to dry for two hours. Only then can work on the object (or the next operation) be continued.

      When is the operation expected to be completed

      Example:

      Since this operation can only be worked on for three hours each day, the estimated completion time (Forecast end) is at 12.00 on 1/25/1997.

      Whether the work for this operation/sub-operation is completed

      Example:

      Once the painting planned in the operation is finished, the employee entering the last confirmation flags the operation as "finally confirmed".

      Whether the reservations still outstanding should be cleared

      Several pots of paint were reserved for the painting work. However, not of all them were used. The employee entering the completion confirmation indicates that the outstanding reservations should be invalidated.

      A free text

      regards

      thyagarajan

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.