Dear All,
Can anyone tell me the how man power calculation occurs with any example.... and do tell me meaning of major fields in Order confirmation screen...
Thanks
DM
hi deepak
if you can pin point your requirments it is easy to explain other than general view, whether you want the manpower cost or manpower itself
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Following are fields that we used to fill during confirmation: plz tell the impact/ relevance of these fields.
Actual Work
Remaining Work
Work Starts on
Actual Duration
Work Ends on
Forecast End
Reason
Confirm. text
TOTAL CONFIRMATION DATA
Following are the fields that are based on some Calculation, can u plz highlight them ???
Cum.Actual Work
ActDuratn
Forecast work
PlannedDuration
i will be gr8ful
RGRDS
DM
hi deepak
yes we have to enter these fields while doing confirmation becaus it has to update in PM component.
<b>Confirmation of Time Data</b>
You can confirm the following time data:
Who processed the operation/sub-operation
Example:
The operation was processed by an employee with personnel number D001760 at work center ME-01 in plant 0001.
How long the work took and the period in which it occurred
Example:
The operation required three hours work. The work was started at 9.00 on 1/12/1997 and finished at 12.00 on the same day.
What activity was performed
Example:
The activity type entered for the operation was "working time".
How much longer work must continue
Example:
The remaining work required for the operation totals five hours.
How much of the operation time was used (duration)
Example:
The operation has lasted five hours (until now).
However, the work duration totals only three hours.
This scenario could occur, for example, if the operation involves painting an object:
The painting work takes three hours. The paint then needs to dry for two hours. Only then can work on the object (or the next operation) be continued.
When is the operation expected to be completed
Example:
Since this operation can only be worked on for three hours each day, the estimated completion time (Forecast end) is at 12.00 on 1/25/1997.
Whether the work for this operation/sub-operation is completed
Example:
Once the painting planned in the operation is finished, the employee entering the last confirmation flags the operation as "finally confirmed".
Whether the reservations still outstanding should be cleared
Several pots of paint were reserved for the painting work. However, not of all them were used. The employee entering the completion confirmation indicates that the outstanding reservations should be invalidated.
A free text
regards
thyagarajan