Former Member
Dec 01, 2007 at 11:06 AM

Budget Exceeding Error

152 Views

Hi,

I've a WBS Element, where in(T code CJ33) the Released Budget value is Rs.5425000 where as the assigned Budget Value is more & i.e Rs.5428078. While creating a Purchase Requisition (Value of Rs.5000), I'm getting an error that Budget exceeded by Rs.3078 ( Rs. 3078 assigned as more + Rs.50000 of PR value=Rs.8078).

How to correct the error & solve the issue.

Next Query is If Release value is Rs.25000 then how it will allow to assign more value than Released value.

Wherras in report CJEO, it is different values for assigned & available values.

Can you please suggest how to overcome this issue. For your reference, please find the attachment.

Thanks in advance.