on 12-01-2007 10:52 AM
Hi friends
My client asking for altenrative items to be picked up automatically , if the main bom component not avaible in stock. guide me in this scenario.
thanks in advance
cotact No: 9871382663
warm regards
bps
Dear,
Please see the help ..read and come back if you need moer help
BOM alternate items
You need to define the following in each alternate item.
Alternative item: group
Consolidation of alternative items within a BOM. Every material in the assembly can be included in the alternative item group.
Use
As soon as you enter an alternative item group, you see an additional dialog box with the following data: ranking order, strategy, usage probability.
You can maintain alternative items in the following situations:
Alternative positions with specific usage probability
These alternative items are incorporated with a specific usage probability. Enter the usage probability for each alternative item in the group, so that:
o dependent requirements are determined in requirements planning
o dependent requirements are changed to a reservation in the production order
Alternative positions as information
You can enter an alternative item for information purposes. This item would then, for example, only be taken into account in situations involving missing parts.
As there should be neither dependent requirements nor a reservation for this item, enter no usage probability.
Procedure
Enter the same character string to denote the alternative items of an alternative item group.
Enter the same strategy for all alternative items in the alternative item group.
Dependencies
Alternative items are valuated in the following way:
Dependent requirements determination
Requirements planning determines the dependent requirements according to the usage probabilities that have been entered.
If the usage probability is 0%, then no procurement is planned for the item. For information purposes, however, dependent requirements with 0 as quantity are created.
Withdrawal posting
You can control the withdrawal posting for the reservation in the production order in the following way:
o Withdrawal according to usage probability (manual change is possible)
o Withdrawal if there is 100% availability
(Check ranking order and strategy)
Example: See Strategy for alternative position
Alternative item: ranking order
Position of an item in an alternative item group.
Use
With respect to withdrawal postings, the ranking order determines which material components from the alternative item group should be taken into account for the reservation in the production order.
Withdrawal according to usage probability
For all items that should be reserved, maintain:
o strategy (value 1 or no entry)
o ranking order (only effects the material sort)
o usage probability
Withdrawal on 100% availability
For all items that should be reserved, maintain:
o ranking order
If you do not enter the ranking order, the system checks the items in the order that they are transmitted to the availability check.
o strategy (value 2)
o usage probability
Example
Three items (0060 und 0065 and 0070) are assigned to an alternative item group and are given the following values for ranking order:
position ranking order
0060 3
0065 2
0070 1
This means that the system reads item 0070 first.
Alternative item: strategy
This value defines how items in an alternative group are selected for withdrawal postings.
This strategy is ignored in material requirements planning (MRP).
Use
The withdrawal posting for the reservation in the production order can be selected as follows:
According to usage probability (manual changes possible)
For all items that you want to reserve, enter:
o Strategy (value 1 or no entry)
o Priority (only influences how materials are sorted)
o Usage probability
Withdrawal if 100% availability
For all items that you want to reserve, enter:
o Strategy (value 2)
o Priority
If you do not enter a priority, the system checks the items in the sequence in which they are transferred to the availability check.
o Usage probability
Procedure
Enter the same strategy for all alternative items in an alternative item group.
Example
Withdrawal if 100% availability (strategy 2)
This strategy uses ATP logic to check availability in the defined ranking order.
Gross requirements: 100 pieces
M UP (%) RO RQ ATP qty Issue qty
A 20 1 20 30 0
B 30 2 30 150 100
C 50 3 50 180 0
Key
M Material
UP Usage probability
RO Ranking order
RQ Requirements quantity
The first material in the ranking order that is supplied 100% on the requirement date is reserved in the required quantity (material B).
If a partial withdrawal is carried out in a production order, when additional partial withdrawals take place, no further checks are carried out for this production order. Additional partial withdrawals result from the alternative item, from which the first withdrawal took place.
If when using strategy 2 none of the alternative items cover the requirements 100%, the availability check for all items will confirm the available. A reservation only occurs for the available quantity
Usage probability in % (alternative item)
Percentage probability that a material will be used in the assembly.
Use
The usage probability is always taken into account for requirements planning.
Procedure
Maintain selected usage probability
Requirements planning for alternative items is based on the usage probability.
Quantities are suggested based on the usage probability for the withdrawal posting according to strategy 1. You can plan in excess for the alternative items since the usage probability is not limited to 100%. You can change the proposed quantities. Maintain no usage probability If you do not enter a usage probability, the alternative item just serves as information that can be evaluated, for example, in a situation with a missing part.
You receive a warning since dependent requirements with 0 as quantity are created.
Examples
Withdrawal based on usage probability
Strategy: value 1
An alternative item group is maintained for each assembly. This alternative item group contains four materials with differing usage probabilities. Dependent requirements are passed on with 100 as quantity.
Material Usage probability (%) Requirement
M-1 70 70
M-2 20 20
M-3 20 20
M-4 0 no requirement
In this case, the materials are planned in excess since the sum of the usage probabilities is greater than 100%.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Try with the field (Alternative item grp)available in BOM item detail screen.
Gopi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.