Hello,
In my project iam using some activities,
for these activities if once i confirm the particular activity then it colour has to change automatically from green colour to red or some thing.
Why because if iam using 80 or 100 activities thn its very difficult for me to find which activity was confirmed.
So pls suggest me in this regard,if thr is any option........
Reward points for Suggestion.
--Prakash.
In which view are you expecting the Activity Colour Change?
Project Builder or Project Planning board?I doubt if you can do it in Project Builder.
But you can change the Gantt Chart (area) Activity actual dates colour,pattern etc.
Use the option Planning Board Assistant->Gantt Chart->Date Display->Set of Dates (Actual)
You mention Actual dates while Confirmation.
Regards
Sreenivas