Hello,

In my project iam using some activities,

for these activities if once i confirm the particular activity then it colour has to change automatically from green colour to red or some thing.

Why because if iam using 80 or 100 activities thn its very difficult for me to find which activity was confirmed.

So pls suggest me in this regard,if thr is any option........

Reward points for Suggestion.

--Prakash.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Dec 04, 2007 at 10:45 AM

    In which view are you expecting the Activity Colour Change?

    Project Builder or Project Planning board?I doubt if you can do it in Project Builder.

    But you can change the Gantt Chart (area) Activity actual dates colour,pattern etc.

    Use the option Planning Board Assistant->Gantt Chart->Date Display->Set of Dates (Actual)

    You mention Actual dates while Confirmation.

    Regards

    Sreenivas

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.