Planning time Fence and Firmed Planned Orders

Former Member
0 Kudos

Hi,

Withing our 30 days planning time Fence, MD04 is showing * mark against the planned order, but when we drill inside the planned order, Firming indicator is missing.

Using M1/ P1 MRP type.

1) Is this a correct oservation?

2) How does it affect the availability check, if we are considering Firmed Planned order to be included in the Av Chk. Will this planned order be considered with the Availability check?

Thnx!

Abhi.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Closed.

Former Member
0 Kudos

Dear,

Let us understand with an example

MRP type = P1

Time fence = 30 days

Let say you have created 3 requirements

01.12.2007 - 100 TO

01.01.2008 - 100 TO

01.02.2008 - 100 TO

Let me know what are you expecting the syatme to do if you run MRP today?