Planning time Fence and Firmed Planned Orders

35 Views

Hi,

Withing our 30 days planning time Fence, MD04 is showing * mark against the planned order, but when we drill inside the planned order, Firming indicator is missing.

Using M1/ P1 MRP type.

1) Is this a correct oservation?

2) How does it affect the availability check, if we are considering Firmed Planned order to be included in the Av Chk. Will this planned order be considered with the Availability check?

Thnx!