on 11-30-2007 8:57 PM
Hi,
Withing our 30 days planning time Fence, MD04 is showing * mark against the planned order, but when we drill inside the planned order, Firming indicator is missing.
Using M1/ P1 MRP type.
1) Is this a correct oservation?
2) How does it affect the availability check, if we are considering Firmed Planned order to be included in the Av Chk. Will this planned order be considered with the Availability check?
Thnx!
Abhi.
Closed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Let us understand with an example
MRP type = P1
Time fence = 30 days
Let say you have created 3 requirements
01.12.2007 - 100 TO
01.01.2008 - 100 TO
01.02.2008 - 100 TO
Let me know what are you expecting the syatme to do if you run MRP today?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.