Activity Type in CO11N

Former Member
0 Kudos

Hallo

I need help in transaction CO11N.

I need in CO11N dynamically to change type activity or work center but I do not see the type activity and work center is gray.

Thanks

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

You can change the activity valures either CO11 or CO11N but niot acivity types.

You can not chage the work center in either CO11 or CO11N.

More over CO11 is old Tcode .

SAP version after 4.6c will not support CO1.

Hope it is clear.

Regards

YMREDDY

Former Member
0 Kudos

Hi

It is error in last update . Please CO11 for CO1.

YMREDDy

Former Member
0 Kudos

Hi

And how is solution now?

How I can change activity type or work center when I need it in confirmation ?

Thanks

Former Member
0 Kudos

Hi

Changing of work center & activity type amounts to changing of master data.

These are not allowed after releasing of the order.

Changes of master data can be effected in production order by the functionality "Read PP master data" even after release also provided :

1.you have not made GI

2.you have not confirmed any operation.

This is Standard SAP functionality.

Hope it is clear to you.

Regards

YMREDDY

Former Member
0 Kudos

Hi,

You can change work center in co11n but this facility was not there in co11 you have to press button 'Actual Data' so that system will take automatically planned values in co11n screen.

reward if it is helpful to you.

AMA.

Former Member
0 Kudos

Thanks for answer.

In CO11 but I do not see activity type. I need to change work center or activity.

But in CO11N I can not to change work center and activity type.

Joki