Employee cost booking other then cost center.

Former Member
0 Kudos

Hi SAP Gurus,

IN SAP HR in order to book the cost of an employee system provides us info type 0027 in which we just mention the cost center on to which we want to book the wage or travel expenses of an employee.

Right now we have a requirement that all the employees who are working on a project there cost should be book against the internal order or WBS element(Internal order are created in asset Mgmt/FI side against a project or if u use PS then WBS element are created in PS against a project and all expenses of projects are booked in internal order or WBS element ).

But in SAP HR we can book the cost of an employee only against the cost center mentioned in info type 027 is there any method through which we can directly book the cost of employee in internal order or WBS element.

Regards

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Rohit,

YOu can directly assign WBS element in 0027 infotype.

Former Member
0 Kudos

Hi,

Thanks for your prompt reply.

In which field i can assign internal order or wbs element coz system only shows cost center field.

Regards

Former Member
0 Kudos

There is a column <b>WBS Element</b> in 0027 inft

You can directly assign WBS element in the column WBS element with % of cost distributed to it.

Former Member
0 Kudos

It is not showing in my system.Can you please tell me where i can do the customization settings for this

Former Member
0 Kudos

Yah , i understand your problem. Will update you once i found the solution