MM - Source List

Hi gurus,

I have a problem with the source list for a material.

This material is provided by another plant of the company code. When I update the source list, I put the validity period, the Plant number that provides the material, the MRP-relevant indicator.

Then the system asks me to put a Purchasing Organization, and when I put it, a Vendor number appears automatically in the "Vendor" field and tells me the this Vendor is not created in this Purchasing Organization.

I don't understand what's happening... If anyone has an idea, it would be helpful.

Thank you

Remi

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2007 at 11:06 AM

    have you created the supplying plant as vendor for STO. I think that is the problem.

    reward if helpful

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2007 at 11:57 AM

    Hi

    If you want to maintain Supplying plant as plant , Please donot enter any vendor details maintain the Supplying Plant under Purchasing Plant.

    If you have laready created the Supplying plant as avendor , Maintain it as Vendor in Source List, with the Purchase organisation Combination.

    Thanks & Regards

    Kishore

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2007 at 11:47 AM

    hi,

    Create the supplying plant as the vendor.

    suppose your plant is SPL1,

    in xk01 transaction, select the account group which is having external numbr range and in the vendor field give the name as supplying plnat name(spl1).

    hope this may help you,

    regards,

    srinivas

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.