hello guys,
material A is produced in in plant X. the same material A is procured from Plant Plant X to plant Y with special procurement 40.
when i raise the the requirement for plant Y, a planned order is generated in plant X, now when i raise the requirement for plant X, i want one collective planned order for both the plants. but i am getting 2 planned orders, one for plantX and the other for plant Y. may i know what setting in material master should be done.
thanks all.
sanjeev
you need to change your lot size indicator in material master mrp1 view from EX to monthly or weekly or daily depending on your requirement
If it is monthly then system will create a order for all the requirement in that month. requirement may be from plant A or plant B for material X.