Dear all,
We have already created production order. Then we make changes in material master. e.g. By mistake we assigned special procurement key for upper level material of BOM insted of lower level item. We modified the master.
Material issue and confirmation is done for lower level material. While confirming upper level material it is giving error ....
Now How to reconcile the system becaz we have already created production order ? How to remove SPK from prod. order ?
Hi Kishor,
After correcting the material master, when you see the BOm componets of that production orders, GO TO- OVER VIEWS - COMPONENT, select the component and double click. You will be directed to material master. Check whether yr settings have taken effect or restirct processing of the order by TACO. And issue a new order.
Rgds,
Umesh
Hi
Read PP master data can be carried out if
NO GI taken place
No confirmation taken place.
for the particular production order.
The problem is for the production order for top level material.
The production order for this material should be free from above.
Try to revrse all Goods movements. & cancel confirmations if any for this ( higher level material production order )
Then carry out" Read PP master Data." for this order.
Try this.
Regards
YMREDDY
Kishore,
Pls let us know the excat SPK used and what error you are getting while confirmation?
Regards,
Prasobh
Add a comment