on 11-30-2007 7:49 AM
Hello,
We are working with cost collector, so when we execute the transaction CK11N in order to calculate the cost of the material we can see the cost comps that have been customized in transaction OKTZ.
We can see the cost comps because this a planning cost. Nevertheless, if we want to see cost comps of REAL COSTS we cant. So, our client wants to have the cost comps of real cost of a group of materials.
Anybody knows if is possible to obtain the cost comps of real cost with cost collector (of a group of materials).
Thank you very much in advance for your information.
Patricia Guevara.
Hi,
This is just standard cost run and we get only planned values only. Once the production order executes then we will get the actual cost or real cost get executed and we can see in the report with Planned and Actual and the Varinaces between them if any.
Regards
Balaji
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Try creating a costing variant which has a valuation variant rhat points to appropriate material and activity prices. Current month activity prices may not be available, but you may point to previous period activity prices.
As far as the material goes, you can use the valuation variant to point to Purchase Info records, where you can maintain the latest updated prices.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you very much, we know that with the material ledger we will obtain this information but we don´t want to activate it (the material ledger). So we want to obtain this information without the material ledger.
Anybody knows if is it possible?
Thank you very mucxh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Thank you for the information. We know that when we execute the production order we can obtain the actual cost or real cost.
Nevertheless, our client want the COST COMPS (customized in transaction OKTZ) of the REAL cost.
Maybe anybody knows if is possible to obtain this information and how can to obtain ir.
Thank you very much.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.