Hello
Do we need to maintain PIRs ( MD61) in REM cycle, if yes in<b> what way does PIRs(MD61) help in REM cycle</b>
As we can maintain the same PIRs in MF50 (Planning Table ) , instead of
maintaining in MD61
Also in MD61 or MF50 - PIRs are being maintained manually, there is not much effect
Any suggestions
Thank you
Hi Eshwer.
In REM cycle, normally we can maintain PIR directly in the planning table MF50 but for a confirm requirement with out sales order you also can maitain the requirement in MD61, go to edit and make yr plan synchronous to sales.
Thats it.
Rgds,
Umesh
It is same whether you maintain requirement in MF50 or MD61. Actually, It depends on your business process. As example, if you maintain SOP and you have already created and confirmed production plan with sales people then you can transfer its production plan to demand management (MD61). So, from this you can run planning table for REM. But if your business doesn't need SOP or Demand management, then you can just make requirement manually on planning table.
Add a comment