We are currently looking at our off site backup stratergy and I have been asked a question which I am not sure what the answer is. Basically what I want to know is if we only had copies of our ECC PRD and BW PRD systems could we do an copyback and create a new ECC DEV & QAS and BW DEV & QAS?

I would have thought no for DEV systems, but yes for QAS systems as DEV could contain a lot of config work untransported.

Any help of official SAP notes would be great!

Thanks in advance

Phil

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Nov 29, 2007 at 09:12 PM

    HI phil,

    If i understand your question properly, then the answer is we never copy PRD to DEV. Always PRD to QAS. But, some people do that as well. It just not recomended by SAP.

    Thanks,

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.