Attachments from R/3 into SRM

Hello everyone -

I have seen a lot of posts regarding the use of attachments from SRM into R/3, but I have found limited information regarding attachments from the back-end into SRM. The client is going to use SRM 5.0, and has multiple back-end systems.

Any help or information regarding how to do this would be very helpful.

Thanks!

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Nov 29, 2007 at 02:36 PM

    Hi,

    If you are talking about BBP_EXTREQ_TRANSFER with attachment, it is not standard in SRM50 but it will come in future release.

    Regards,

    Masa

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 29, 2007 at 03:33 PM

    Hi

    <b>Please go through the related links / SAP OSS Notes below -></b>

    <b>Note 1057932 FAQ: Atachment transfer to backend, Required Configurations</b>

    Note 1010855 FAQ Common questions regarding the Rfx Information Tab

    Note 1001130 FAQ - Attachment questions (Buyside)

    Note 1030777 Follow-on note to 848909. Size of the table BBPCONT is big

    Note 989660 FAQ - RFx Supplier Questions - Attachments

    Note 1041080 UWL configuration

    Hope this will answer your queries. Do let me know.

    Regards

    - Atul

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2007 at 02:33 AM

    Hello Scott,

    We understand yr pain.

    As Masa had already said it is not a standard feature of 5.0 and would be available from 6.0 onwards.

    We also need the same functionality in 5.0 for our customer and working on some inputs given by Christophe.

    pasting here for yr ref.

    ***********************************************************************************

    Attachments of PR sent to SRM should be transfered as well.

    In SRM, the inbound attachment references are processed by function BBP_ATTACH_CONTENT_WEBGET. This function will read sent doc URLs and create corresponding doc in SRM SC item attachment.

    I said BBP_ATTACH_CONTENT_WEBGET is in charge of reading external documents and creating them as SRM attachments.

    It is not related to cFolders specifically.

    This function is used in the external requirement scenario during the inbound SC creation in SRM: it reads backend documents, would it be a 4.6C or an ECC6.0 system.

    ECC will send URL of your DMS docs, and SRM will try to process those URLs.

    So debug the external requirement flow: starting in R/3 (check that ECC sends doc URLs), going into SRM (with an RFC dialog user), and break point in function BBP_ATTACH_CONTENT_WEBGET.

    ******************************************************************************

    BR

    Dinesh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.