PM - PP Integration

Which are the integration points between SAP PM and PP module?

Can the Production planning and Maintenance planning have any contact points?

Can the shutdown need from Maintenance person be examined by Production person?

Thanks,

Kedar

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Dec 01, 2007 at 07:05 AM

    Kedar,

    this query is already answered several times before.

    https://forums.sdn.sap.com/click.jspa?searchID=-1&messageID=3986430

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 29, 2007 at 09:38 PM

    kedar

    Which are the integration points between SAP PM and PP module?

    Answer - The PP work centers are integrated in PM , whenever you Schedulen the Maintenance on the PP work center , In the Capacity planning the PP work center Capacity is Blocked for the duration of maintenance.

    Can the Production planning and Maintenance planning have any contact points?

    What exactly you mean by the contact points could you be more specific

    Can the shutdown need from Maintenance person be examined by Production person?

    Yes It can be seen in the Capacity plan for the Work Center

    Thanks,

    Kedar

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 30, 2007 at 06:22 AM

    Hi Kedar,

    The PP & PM have integration point as Work Center (in location tab of equipment master data, we mention the work center). This work center is nothing but the production machines.

    So, whenever we schedule maintenance plan for a reference object, whichever the work center is maintained in the master data of that reference object gets blocked & cannot be used by production. At the time of production planning, system automatically skips those dates for the work center & does the production planning.

    So anytime production planning is done by the PP guy, he / she can see that which work center is blocked by PM.

    Hope this helps you.......

    Regards..........

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.