on 11-29-2007 7:08 AM
Hi all,
I have the following scenario for which a problem is being faced by me:
I a maintenance order operations are assigned; these operations can be related to one another by maintaining operation relationships (FS/FF/SF/SS).
I am able to do all these without any problem. The issue is
For example,
the predecessor operation is 0010, successor operation is 0020
Relatioship type : FS
Offset rel. ship: 10.0 Min
Work center : xxxxxx
Plant: xxxx
After this the order was scheduled once agin.
Now as per the setting done, system should not allow me to do operation confirmation of operation 0020 without confirming operation 0010 first.
But system is allowing me to confirm operation 0020 without giving any warning or error.
Is there any IMG steting need to be done to overcome this issue.
Moreover I found that the "Successor Ind." field in the relationships screen of an operation is masked. Is this the problem?
I mean if this filed can be unmasked so that I can activate the check box as required by me?
Your valuable suggestions are most requested
Thanks and best regards.
Kannan J
Hi,
I guess I made a mistake. Mr.Pavalavel is right.
My regards to Pavalavel.
Muraleedharan.R
091 9880028904
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check the following customization settings:
Project system->Operational structures->Network->Settings for network activities ->Define control key (Transaction OPSU) , select the control key used in your activity type and see whether "Confirmation" is" required". Most likely it is optional.
Make confirmation "required" and then your problem should be resolved.
If the problem is solved, kindly acknowledge the same.
Muraleedharan.R
091 9880028904
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kannan,
I think you are going in wrong direction. The relationships are meant only for scheduling purpose and has nothing to do with confirmations. Confirmation required config is used to define if the operation can be confirmed or not. It does not validates whether the previous opertion is confirmed or not. So You need to go for a development to do this validation, when an opertion is confirmed.
Try the finding which user exit solves ur requirement from this list
CONF0001 Enhancements in order confirmation
CONFPI01 Process order conf.: Calculate cust.specific default values
CONFPI02 Process order confirmation: Customer spec. input checks 1
CONFPI03 Process order conf.: Cust. spec. check after op. selection
CONFPI04 Process order conf.: Customer specific input checks 2
CONFPI05 Process order conf.: Cust. spec. enhancements when saving
CONFPI06 Process order confirmation: Actual data transfer
CONFPM01 PM/SM order conf.: Determine cust. specific default values
CONFPM02 PM/SM order confirmation: Customer specific input checks 1
CONFPM03 PM/SM order conf.: Cust. spec. check after op. selection
CONFPM04 PM/SM order conf.: Customer specific input check 2
CONFPM05 PM/SM order conf.: Cust. specific enhancements when saving
CONFPP01 PP order conf.: Determine customer specific default values
CONFPP02 PP order conf.: Customer specific input checks 1
CONFPP03 PP order conf.: Cust. specific check after op. selection
CONFPP04 PP order conf.: Customer specific input checks 2
CONFPP05 PP order conf.: Customer specific enhancements when saving
CONFPP06 PP Order Confirmations: Actual Data Transfer
CONFPP07 Single Screen Entry: Inclusion of User-Defined Subscreens
CONFPS01 PS confirmation: Determine customer specific default values
CONFPS02 PS confirmation: Customer specific input checks 1
CONFPS03 PS confirmation: Customer specific check after op. selection
CONFPS04 PS confirmation: Customer specific input checks 2
CONFPS05 PS confirmation: Customer specific enhancements when saving
Regards,
Pavalavel.
Kannan,
On the maintenace order, The relatioships are the order screen are more for planning purpose and dont really control the confirmation process. Based on the relationship thats maintained you can dispatch just the first operation on the order to be completed and then dispatch the second operation, once you assign employees to it.
However if your requirements are such that you would want the confirmation to be posted in order, you can definetly put additional custom checks(confirmation user exists) on the same and accompish your requirement.
Hope it helps.
Thanks
Narasimhan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.