Hi,

We have Del Complte indicator in both PO and Schedule Agreement but is not available for Contracts.

So how can we manually close a contract? (I know the system will consider it as closed when the qty or the amount reaches it's target value) The client wants to close the contract earlier manually?

Also how can we see which contracts are closed?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

One option is to set the item to Blocked (Not Deleted) in the contract. This way, you can track what contracts are closed early in the standard reports. Blocking is also stored in the deletion indicator as a different character.

Lakshman

Answers (2)

Answers (2)

Former Member
0 Kudos

Thanks

Former Member
0 Kudos

Hi,

Blocking the items is the best option. However, you may reduce the target amount to the currently reached value, making it not available for further release of POs and no open target value left...