why does the planned cost of WBS not been reduce?

Former Member
0 Kudos

My project is builded as following

wbs: T-20051.3

activity: 3000

material componet: T-20100

material componet: T-20210

  • activity is assigned to wbs, two material is assigned to activity.

T-20100 and T-20210 procurement type :Requisition + reservation for WBS elemen

I look cost planned report use following transaction:

S_ALR_87013533 - Plan/Actual/Commitment/Rem.Plan/Assigned

cost planned of Activity 3000 is 130460 EUR,

this value is exactly equal to sum between material T-20100 cost planned and

material T-20100 cost planned that is calculated by quantity multiplied standard price.

after I delete material component T-20100 and T-20210, as a result, the cost planned of activity 3000 is not changed, that is, it value is still 130460 EUR,

I think its value should become to zero. why not be changed ? can you tell me?

thank you expert.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hai Yongguo

Have u got the result ???

Regards

PP

Former Member
0 Kudos

Try to regenerate project CJEN & Then see if it works

Former Member
0 Kudos

Hai

After deleting the material have u saved the project. Open the Project using CJ20N - go to the activity and click on the activity - where the material is been added and deleted.

In the same screen - Go to Edit - Costs - click on Calculate costs. System will calculate the costs.

Again go to Edit - Costs - Plan/Actual - Click on Activity / Element.

If the cost is been calculated - will reflect the planned - actual costs here in this activity which u can verfiy whether in S_ALR_87013533 reflecting the same or different.

Check S_ALR_87013533 once again by refreshing the tcode.

ENJOY SAP PS. Award Point if useful.

Regards

PP