Dear PS Gurus,
Request kindly let me know whether we can customise/configure the Network Activity dates (Must start on & Must finish on ) mandatory fields in PS.
Currently, we are having standard templates in network, whenever the project is created, immediately network is created by user taking the standard template and assign the same with WBS element/Project Definition. In Network, standard template activities are copied into the Network, in Network, internal activities are defined, and user has to give dates (must start on & must finish on), but since it is not mandatory fields, dates are not given and saved the network.
I would like to make the Mandatory fields of dates for user to duly put the dates and save the network. Pl help in how this can be done?
thanx in advance
regadrs
srihari