Machine availability Report

Dear All,

Plz tell me T/code or any procedure.......to calculate Machine availablity,,,,,,or if any like functional location availability/????

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Posted on Nov 27, 2007 at 08:15 PM

    Hi Deepak,

    what do you mean with "availability report"?

    Do you mean status ???

    Regards

    silvia

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 28, 2007 at 04:33 AM

    Hi Deepak.......

    Plz clear that what u exactly mean by machine availability.

    Regards.......

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 21, 2011 at 09:26 AM

    Hi Deepak ,

    About the Machine availability, Whether Production planning module is being implemented at your client and if it is, are they creating a work center for the equipment, and if they are, they must be maintaining the available capacity and whenever the equipment is under maintenance/ production, capacity requirement would be generated for the equipment. Using Capacity requirement reports, you can check the availability of equipment in the last month or any time period.

    If PP is not being implemented, create a Processing unit work center for the equipment and record all of the capacity requirements yourself.

    Second approach could be by using a measuring counter for the equipment and recording the running hours for the equipment each day, then you can create a customized report showing the total capacity of equipment, the running hours, the available hours.

    Regards,

    Muhammad Usman Kahoot

    Edited by: Usman Kahoot on Apr 21, 2011 11:28 AM

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Apr 21, 2011 at 10:45 AM

    Some organisations calculate the equipment availability as under

    Equipment Availability in % = (Actual Availability / Expected availabiltiy) X100

    where

    Actual availabilty (Hrs) = Expected availability (Hrs) - Downtime due to breakdowns (Hrs)

    Expected availability (Hrs) = Total calender hours - Preventive maintenance hours

    It is upto one organisation how it defines it, to indicate the efficiency of maintenance function.

    Regards

    Jogeswara Rao

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.