Hi SAP Gurus,

Is there any way to create a delivery(PGI) without any stock moment (i am using a Z movement tye). i e stock sholud not decrese.

This I need to To update a cost account.(which is only possible with movement type.) if I use a movement type stock get decresing. which my does not needed.

Thanks in Advance

Ram

Accepted Solutions (1)

Accepted Solutions (1)

Lakshmipathi
Active Contributor
0 Kudos

Dear Ramu

It is not possible to do PGI without a movement type.

Also can you please let me know what warrants you to do that.

Thanks

G. Lakshmipathi

Former Member
0 Kudos

Hi Lakshmipathi,

Thanks for the reply,

Process is:

If A customer informs that Material A is defevtive or not working,

Wht the we do is, we deliver(order/delivery/billing) material A to the customer and a return order is created for the material for which a return is anticipated from the customer. The customer is informed of the same with a request to return the product in a stipulated time frame.

If the customer returns the product, the return delivery is booked followed by creation of a credit memo in the system. and we come to know that whether the material is under warrenty or not after the PGR (receipt),

if it is under warrenty, Cost must be booked under cost account( no revenue)

( which is only possible through at the time of PGI with a movement type), since Material already delivered to the customer, we cannot create a delivery with material movement.

if there any way to revese the inventory at the time of PGI.(issue and retun shold happen at same so there will not be any impact on stock level)

please let me know is there any other way

Answers (1)

Answers (1)

Former Member
0 Kudos

hi,

creating delivery is diff than doin PGI, so if its only delivery creation than there is no issue. but if u want certain accnts to be hit then i do not think its possible w/o mat mvmnt.

saurabh

Former Member
0 Kudos

Hi

Thanks for the reply,

Process is:

If A customer informs that Material A is defevtive or not working,

Wht the we do is, we deliver(order/delivery/billing) material A to the customer and a return order is created for the material for which a return is anticipated from the customer. The customer is informed of the same with a request to return the product in a stipulated time frame.

If the customer returns the product, the return delivery is booked followed by creation of a credit memo in the system. and we come to know that whether the material is under warrenty or not after the PGR (receipt),

if it is under warrenty, Cost must be booked under cost account( no revenue)

( which is only possible through at the time of PGI with a movement type), since Material already delivered to the customer, we cannot create a delivery with material movement.

if there any way to revese the inventory at the time of PGI.(issue and retun shold happen at same so there will not be any impact on stock level)