How to create a Reservation for my production order

Hi,

I have a production order for that I need to purchase 2 materials. but my problem is when the material come there is no reservation for my production order. someone can take it for another production order. How can I do that the system create a reservation after the GR

Thank

Add a comment
10|10000 characters needed characters exceeded

Related questions

5 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 03:54 PM

    Dear,

    When you create and release production order, the reservation is created for that order. Now you should first activate the Avelability check in production order.

    It is PP configuration

    Then you need to activate dynamic aveailability check in goods issue in MM configuration.

    Hence if the stock is reserved for your production order, then no one can issue and system will give error message.

    please come back if required.

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 24, 2007 at 07:53 AM

    In the configuration of "Scope of Check" select the corresponding Checking group and checking rule and click on detail button. Set X indicator for include depender reservations.

    Then once you create the order, component will get reserved and it will not allow to issue to other order.

    Hope your issue has been resolved

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 24, 2007 at 07:54 AM

    In the configuration of "Scope of Check" select the corresponding Checking group and checking rule and click on detail button. Set X indicator for include depender reservations.

    Then once you create the order, component will get reserved and it will not allow to issue to other order.

    Hope your issue has been resolved

    Purna

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 24, 2007 at 09:08 AM

    In the configuration of "Scope of Check" select the corresponding Checking group and checking rule and click on detail button. Set X indicator for include depender reservations.

    Then once you create the order, component will get reserved and it will not allow to issue to other order.

    Hope your issue has been resolved

    Purna

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 24, 2007 at 07:35 PM

    Please come back?

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.