Hi everybody! I am working in ERP 4.7 and I need specification services for a SAPScript PO.

When I check table EKPO I have field Package Number and when I go to table ESLL I put Package Number field and when I check field KTEXT1 I don´t have specification service text, this field is empty.

What can I do?

Thanks in advance

Rose

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Nov 23, 2007 at 09:05 PM

    You have to use first table EKPO, then EKLL and with subPackage Number you have to go to table EKLL again.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.