Hi sap gurus,

How can I create a early lot inspection

Cheers,

Krishna

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 08:00 AM

    Hi

    If it inspection type 04 , you can set in IMG step Default values for inspection lot.

    Then system will create the inspection lot during production order creation/release.

    You can go ahead with this etting.

    Regards

    YMREDDY

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 09:54 AM

    In material master in QM View for Insp Tpye 04 ,you can select the option of Early lot creation.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi all,

      Inspection type 04 is for goods receipts inspection from production order, and the lot will be created only after the confirmation of the last operation.( not with order release).

      You have to create 03 inspection type (in process inspection) to achieve this.

      Regards

      '

      Rajesh

  • author's profile photo Former Member
    Former Member
    Posted on Nov 23, 2007 at 01:27 PM

    I hope it is for raw material, I think you are specking about the inspection at vendor's place...called source inspection.

    <b>Source inspections</b> are performed upon request and with the participation of the customer or sold-to party. A source inspection can performed by the receiver of the service, the vendor in the presence of the receiver or by a person or third party appointed by him.

    If the inspection lot for the source inspection is rejected for goods receipt item, the Customizing settings for the QM in procurement control key determines whether:

    A goods receipt posting is not possible or

    A quality notification is not created and a new inspection lot is created

    For more information, see Triggering Source Inspection.

    For this to happen we need <b>quality info record</b>

    You normally create a quality info record after you have maintained the QM-specific data in the material master. A vendor master record must also be available.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Dec 05, 2007 at 12:43 PM

    This thread has been answered

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.